Sitaram Sankar Patil v. the State of Maharashtra through Secretary and Ors.
Case brief
What is this about?
MLRC 1966 S.257 revision application; direction to State Government to decide revision application within three months; condonation of delay not pressed; revision filed shortly after receipt of impugned Deputy Commissioner order dated 22.03.2024 in Appeal S.R.106/2022/24 under S.247; interim relief to be considered within four weeks; Bombay High Court WRIT PETITION NO.287 OF 2025; A.S. Chandurkar & M.M. Sathaye, JJ.; decided 27 January 2025; relied on Santoshkumar Shivgonda Patil v. Balasaheb Tukaram Shevale (2009) 9 SCC 352.
What did the court decide?
Writ petition disposed of with a direction to respondent no.1 to decide the petitioner's Revision Application within three months of receiving a copy of the order; any request for interim relief to be considered within four weeks of receiving a copy of the order, after hearing all parties; contentions of parties kept open.