Nira Deoghar Dam Rehabilitation Development Farmers Association v. the State of Maharashtra through Secretary and Ors.
Case brief
What is this about?
Short adjournment order dated 11-08-2025 of the Bombay High Court (Appellate Side, Civil Jurisdiction) in Writ Petition No. 2847 of 2025 (Nira Deoghar Dam Rehabilitation Development Farmers Association v. State of Maharashtra through Secretary and Ors.), heard with Interim Application No. 7017 of 2025 (Shivaji Dagdu Kank and Ors. v. the Association and Ors.). Bench: Revati Mohite Dere and Dr. Neela Kedar Gokhale, JJ. Matter stood over to 10/09/2025; interim order, if any, to continue till then. No statutes, precedents, issues, holdings or amounts.
What did the court decide?
Matter stood over to 10/09/2025 due to paucity of time; interim order, if any, to continue till then. ¶17