Charity Commissioner Greater Mumbai; change reports; Section 22 Maharashtra Public Trust Act 1950; M.I.G. Cricket Club; consent order; compliance timetable; two weeks / four weeks / four months deadlines; public trust change reports pending since 2010; writ petition disposed; no costs; Bombay High Court OOCJ 2025.
What did the court decide?
Consent-based time-bound directions recorded: Respondents to communicate pending compliances within two weeks of upload of the order; Petitioner to satisfy them within four weeks of such communication; Respondents to dispose of the Change Reports (2010-2024) within four months of satisfaction of compliances; no order as to costs. ¶22