Raghavendra Construction Company Pvt. Ltd. v. Municipal Commissioner Mcgm
Case brief
What is this about?
Neutral citation 2025:BHC-OS:9981-DB. Search terms: sanction of new Road Line (RL)/new public street; Section 291 and Section 291(a) Mumbai Municipal Corporation Act 1888; Section 291 read with 294 MMC Act; Section 297 MMC Act; Regulation 33(10) Clause 7.1 DCPR 2034; Section 37 Maharashtra Regional Town Planning Act 1966; Sections 91, 296 MMC Act; SRA no objection; Slum Rehabilitation Scheme (SR Scheme); declaration of public street; gross non-application of mind; opportunity of hearing implied into statutory provision; principles of natural justice; judicial review; Dr. Abraham Patani (2023) 11 SCC 79 distinguished; remand for fresh decision; hearing by CEO/SRA; Malad, Gen. A.K. Vaidya Marg, CTS No.610A/1B/1, 610A/1B/2, CTS No.677/A/1(part); Resolution No.592 dated 26 September 2024; interim order dated 5 March 2025; writ petition partly allowed and disposed.
What did the court decide?
All MCGM decisions sanctioning the new public street/RL through the Petitioner's plot set aside; MCGM at liberty to take a fresh decision under Section 291 MMC Act in consultation with SRA; CEO/SRA to afford hearing to the Petitioner and Respondent Nos.4 and 5 before recommending sanction (parties to appear on 8 July 2025); CEO/SRA to give comments within four weeks and MCGM to decide on or before 11 August 2025; interim order of 5 March 2025 to continue till 11 August 2025; all contentions kept open before CEO/SRA.