All Services Global Private Limited v. Union of India through Ministry of Petroleum and Natural Gas
Case brief
What is this about?
Writ Petition No.1971 of 2024, High Court of Bombay (OOCJ), Division Bench (Revati Mohite Dere & Dr. Neela Gokhale, JJ.), decided 02-04-2025. All Services Global Private Limited & Anr. v. Union of India, ONGC Ltd. & Anr. Outside Expert Committee (OEC); Clause 27.1 conciliation; Clause 27.2 arbitration; agreement dated 17-04-2013; demand letter dated 20-06-2023; undertaking to constitute OEC; conciliation to conclude within 90 days; petition disposed on consent/settlement; liberty to invoke arbitration clause on failure of conciliation; merits not examined, contentions left open; Companies Act, 1956.
What did the court decide?
Respondent Nos.2 and 3 to constitute the Outside Expert Committee (OEC) in accordance with Clause No.27.1 of the contract dated 17th April 2013, with conciliation to be completed not later than 90 days from the date of its constitution; parties at liberty to invoke the arbitration clause if the conciliation process fails.