Vivek Singh and Ors. v. Union of India through Ministry of Railway and Ors.
Case brief
What is this about?
Bombay High Court writ petition disposed; railway fencing/construction dispute; salt pan land Survey Nos. 117 and 118, Village Umela/Umele, Taluka Vasai, District Palghar; boundary demarcation and identification of land; direction to DILR/Deputy Superintendent of Land Records, Palghar to survey Survey Nos. 115-118 within eight weeks; survey report to parties; 48-hour advance notice; equal survey fees; Railways reply affidavit (Divisional Engineer Estate/North); Mumbai Rail Vikas Corporation respondent no.3; Vasai Virar Municipal Corporation communication dated 18 April 2022 re acquisition; Article 226 Constitution of India; contentions kept open; no costs.
What did the court decide?
Petition disposed of (no costs) by directing respondent no.5/DILR to survey and measure Survey Nos. 115, 116, 117 and 118 at Village Umele, Taluka Vasai, District Palghar within eight weeks; survey report to be furnished to all parties; minimum 48 hours' advance notice of the survey to the parties; parties to provide documents to the survey team; petitioner permitted to file a formal application with the DILR within one week; DILR fees/charges borne by the parties in equal proportion; all contentions on the survey and respective land rights kept open for appropriate proceedings.