Jayantilal Bhimshi Gangar v. the Registrar - Nclt - Mumbai
Case brief
What is this about?
NCLT Mumbai delay and expedition; mandamus under Article 226; Company Petition No. 4065/2019 with Company Application No. 205/2021; earlier writ OS-WP-LD-VC-240-2020 direction of 24 August 2020 (eight weeks) unimplemented; Miscellaneous Application Nos. 3803/2019 and 806/2020 disposed; 12-week outer time limit; linked Company Petition No. 403/2019 (Writ Petition No. 1481/2024); Bombay High Court writ petition disposed; compliance listing 24 September 2025.
What did the court decide?
Petition disposed of on the terms that the NCLT is requested to hear and dispose of Company Petition No. 4065/2019 along with Company Application No. 205/2021 as expeditiously as possible and in any event within 12 weeks from receipt of the order; it is open to the NCLT to consider disposing of it together with Company Petition No. 403/2019; all parties, including the petitioners' counsel, assured cooperation; matter stood over to 24 September 2025 for recording compliance.