Bombay HC WP 1183/2025 (decided 12-06-2025): recovery of undisputed contractual dues of Rs.7,22,704/- by proprietary-concern contractor under work order dated 30-07-2024 following tender notice dated 20-02-2024; completion certificate dated 23-09-2024 not disputed by State respondents (officers of Kurla PWD and ESIS present); direction to pay within six weeks with 6% interest on default; useful on prompt payment of admitted bills of State instrumentalities.
What did the court decide?
Direction to respondent nos. 2 to 6 to pay Rs.7,22,704/- to the petitioner within an outer limit of six weeks; on failure, the amount to carry interest at 6% from the date it became due till payment. ¶27