Nandkumar Infrastructure LLP Thr. Authorised Person v. the State of Maharashtra and Ors.
Case brief
What is this about?
tender clubbing; clubbing of tenders; Public Works Department Government Resolutions 17.12.2016 and 19.09.2017; continuous length of road; works distinctly apart; internal roads; laying of drainage line; Nandkumar Infrastructure LLP; State of Maharashtra; Kolhapur Circuit Bench; interim directions; Affidavit-in-Reply three weeks; grant of tender subject to outcome of petition; listed 11.11.2025.
What did the court decide?
No final relief; interim directions only: Respondent Nos. 2 & 3 to file Affidavit-in-Reply within three weeks; Petition listed on 11th November 2025; grant of tender made subject to the outcome of the Petition. ¶21