Case brief
What is this about?
Administrative common order of the Bombay High Court dated 29-07-2025 (digitally signed 01-08-2025) adjourning Appellate Side and Original Side matters listed on the Daily and Supplementary Board due to paucity of time, rescheduling them per CIS to dates from 12/08/2025 to 24/09/2025; ad-interim/interim relief operative on the order date expressly continued till respective next dates; coram Shree Chandrashekhar and Manjusha Deshpande, JJ; no litigants, statutes or precedents engaged.
What did the court decide?
Administrative adjournment of all listed matters to CIS-fixed dates (ranging 12/08/2025 to 24/09/2025), with continuation of operative ad-interim/interim relief till the respective next dates. ¶9