MCA (ARBN) 197/2025, Bombay High Court Nagpur Bench, order dated 11.11.2025 by Nivedita P. Mehta, J. Applicants M/s Green City Builders and others (adv. S. Zia Quazi) obtained time from respondents M/s Kardhar Finance Pvt. Ltd. & another (adv. A.S. Dabadghao) to amend the cause title regarding the array of respondents, a Director having been inadvertently impleaded in his personal capacity. Direction: amendment and service of amended memo within two weeks; next hearing 27.11.2025. Procedural/interim order only; no merits, quantum or precedent discussion.
What did the court decide?
Interim relief at this hearing: time granted to the appellants to amend the cause title (array of respondents) within two weeks and serve the amended memo on the respondents; matter carried forward to 27.11.2025 for further consideration. ¶¶10