The New India Assurance Co. Ltd. v. Mr. Satish Kumar Umakant Dubey and Anr.
Case brief
What is this about?
Bombay High Court, Civil Appellate Jurisdiction; Interim Application No. 9219 of 2024 in First Appeal (St.) No. 23005 of 2023; The New India Assurance Co. Ltd. v. Satish Kumar Umakant Dubey & Anr.; condonation of delay; delay of 233 days in preferring appeal; insurance company applicant; notice to Respondent No.2; private notice service; copy supplied 17 December 2024; direction to file additional affidavit; next date 3 March 2025; Sharmila U. Deshmukh, J.; order dated 17 February 2025.
What did the court decide?
No decision on condonation of delay at this stage; Applicants directed to file an additional affidavit elaborating the explanation for the 233-day delay within two weeks, and the matter listed on 3 March 2025. ¶17