Lloyds Engineering Works Ltd. v. Transparent Energy Systems Private Ltd. through the Liquidator Vijendra Kumar Jain
Case brief
What is this about?
Section 34 Arbitration and Conciliation Act 1996; wrongful encashment of performance bank guarantee; restitution versus damages; proof of loss not required; perverse award; additional evidence; belated documents; credence of evidence; delay in pronouncement of award; Section 29A; Covid-19 lockdown; unexplained delay; Lancor Holdings followed; Kisan Sahakari Chini Mills distinguished; Jackie Kakubhai Shroff distinguished; Municipal Corporation of Greater Mumbai v B.E.S.T. Workers Union; Gayatri Balasamy severance of award; Section 31A costs; reduction of costs; Commercial Arbitration Petition; Bombay High Court; Lloyds Engineering Works v Transparent Energy Systems; PBG invocation; liquidated damages; counterclaims rejected in first award.
What did the court decide?
Arbitration Petition allowed in part: the direction to pay costs of Rs.34,60,647 set aside and substituted with costs of Rs.10,00,000 payable by the Petitioner to the Respondent; rest of the Award (Rs.23,97,000 with 12% interest) upheld; Interim Application No. 717 of 2025 disposed of as not surviving.