Cobra Instalaciones Y Services S a v. Maharashtra State Electricity Distribution Company Limited
Case brief
What is this about?
MSEDCL v. Cobra Instalaciones Y Services; Bombay High Court; Commercial Arbitration Petitions Nos. 39, 43, 59, 60, 67 of 2022; interim applications for withdrawal of amounts deposited with Prothonotary and Senior Master; conditional leave subject to bank guarantee of a nationalized bank; accrued interest plus further interest at 7% per annum on principal and interest for one year; bank guarantee deadline 20 January 2026; replies by 5 December 2025; Kamal Khata, J.; order dated 2 December 2025.
What did the court decide?
Conditional leave to the Applicants/original Respondents to withdraw the amounts deposited by the Petitioner with the Prothonotary and Senior Master, High Court, Bombay, permitted only against furnishing of a bank guarantee of a nationalized bank covering the withdrawn amount, accrued interest thereon, and further interest at 7% per annum on the aggregate (principal + interest) for a further period of one year, the bank guarantee to be furnished on or before 20th January 2026.