Mohan P Uttarwar v. Palm Grove Beach Hotels Private Limited
Case brief
What is this about?
Bombay High Court (OOCJ), Commercial Suit No. 71 of 2024, Palm Grove Beach Hotels Pvt Ltd v Raheja Plaza Premises Chs Ltd, heard along with 20 interim applications (Nos. 3457, 3062, 5600, 1506, 1279, 1384, 1387, 522, 524, 1295, 1383, 1386, 1574, 523, 725, 537, 517, 518, 516 of 2024/2025 and Lodging No. 36084 of 2024) involving ITC Limited, Raheja Plaza Premises CHS Ltd, Mohan P Uttarwar, Hacienda Leasing And Infotech, Mita Nalin Doshi, Nikhil Jain, Metacan Industries, Panache Digilife Ltd (fka Vardhaman Technology), Mangrolia/Magrolia Leasing And Infotech and BBAS Association against Palm Grove Beach Hotels. Order dated 18 November 2025 by Justice Somasekhar Sundaresan: S.O. to 16/12/2025; all ad-interim/interim reliefs operative that day continued until the next hearing date; reliefs not time-limited remain unaffected. Adjournment-only order; no merits, no citations.
What did the court decide?
Post-court order: matters stood over (S.O.) to 16/12/2025. All ad-interim or interim reliefs operative on 18 November 2025 were continued to operate until the next date; reliefs that had not been granted for a limited period remain unaffected. No merits adjudicated.