Order VII Rule 11 CPC; rejection of plaint; maintainability of suit; arbitration clause versus civil suit for simpliciter recovery; Agreement dated 6th April 2010; Statement of admission and denial; withdrawal of interim applications; Commercial Summary Suit; Bombay High Court Commercial Division; Sagar Arts Pvt Ltd v Pragya Vision Pvt Ltd; 2025; Abhay Ahuja J.
What did the court decide?
Interim Applications No. 5880 of 2025 and No. 5885 of 2025 stand disposed as withdrawn; Statement of admission and denial to be filed and served within one week; reply to Interim Application No. 5121 of 2025 (under Order VII Rule 11 CPC) to be filed within two weeks with rejoinder two weeks thereafter; matter listed on 4th December 2025. ¶8