Swarna N Mehra and 2 Ors. v. Jade Construction Pvt. Ltd.
Case brief
What is this about?
Short procedural order of the Bombay High Court (Ordinary Original Civil Jurisdiction), dated 3 October 2025, coram B. P. Colabawalla & Amit S. Jamsandekar, JJ., disposing of Interim Application No.5079 of 2025 filed by Swarna N. Mehra & Ors. (Megha Gupta with Lavanita Chityala, i/b Hedgehog & Fox LLP) for condonation of a 23-day delay in filing Appeal (L) No.1732 of 2024 against Jade Construction Pvt Ltd (Vishal Kanade with Anagh Pradhan, i/b Divya Shah Associates). The Court condoned the delay, ordered removal of remaining office objections within two weeks on pain of dismissal of the appeal without further reference, and made no order as to costs. No statute or precedent was cited and no quantum was involved.
What did the court decide?
Delay of 23 days in filing the Appeal condoned; applicants directed to remove all office objections within 2 weeks, failing which the appeal shall stand dismissed without further reference to the Court; no order as to costs.