Union Bank of India (Erstwhile Corporation Bank) v. Carolya Construction Pvt. Ltd.
Case brief
What is this about?
Attachment lifting SARFAESI Act secured creditor Union Bank of India Carolyn Constructions Pvt. Ltd. Prem Leela Developers execution application Bombay High Court Ordinary Original Civil Jurisdiction interim application reply rejoinder adjourned listed 3 November 2025 Abhay Ahuja EXA 469/2011 IA 4619/2025
What did the court decide?
No substantive relief granted at this stage; the Court directed the Judgment Creditor/Execution Applicant to file reply within two weeks with copy to the others, rejoinder within two weeks thereafter, and listed the matter on 3rd November, 2025. ¶14