Aum Sai Constructions Pvt. Ltd. v. Sanjay Co-Operative Society Thr.Its Chairman and Secretary and Ors.
Case brief
What is this about?
Bombay High Court interim order dated June 24, 2025 by Somasekhar Sundaresan, J. in Arbitration Petition No. 64 of 2022 with Interim Application No. 3346 of 2025; Aum Sai Constructions Pvt. Ltd. (Petitioner, through Jitendra H. Oake) v. Sanjay Co-Operative Society through its Chairman & Secretary & Ors (no appearance for Respondents); extension of time to complete and serve amendments (by July 1, 2025 / July 4, 2025) following June 9, 2025 order granting liberty to amend; listing on July 8, 2025; actions to be taken on downloaded copy from Court website; no statutes, precedents, issues or amounts.
What did the court decide?
Interim procedural relief only: time extended to complete amendments by July 1, 2025 and serve them on the Respondents by July 4, 2025; matter listed for July 8, 2025. The Arbitration Petition itself remains pending.