The State of Maharashtra Represented by the Executive Engineer PWD Panvel v. Atlanta Limited
Case brief
What is this about?
Bombay High Court; IA 2552 of 2025 in COMEX 65 of 2024; State of Maharashtra (Executive Engineer, PWD Panvel) v. Atlanta Limited; interim application disposed; attachment already lifted; execution application reply within two weeks; rejoinder within two weeks thereafter; next hearing 11 December 2025 at 3.30 p.m.; coram Abhay Ahuja, J.; decided 6 November 2025; consent-based disposal; no statutory provisions or precedents cited.
What did the court decide?
No substantive relief; the Interim Application was disposed of following submissions of both sides. Directions issued: reply to the Commercial Execution Application within two weeks, rejoinder within two weeks thereafter; Commercial Execution Application listed for hearing on 11 December 2025 at 3.30 p.m. ¶17