Ganesh Benzoplast Ltd. v. Indorama Synthetic India Ltd.
Condonation of delay – Section 34, Arbitration and Conciliation Act, 1996
Case brief
What is this about?
Bombay High Court, Ordinary Original Civil Jurisdiction; Somasekhar Sundaresan, J.; IA No.2317 of 2024 in Commercial Arbitration Petition (L) No.16340 of 2024; Ganesh Benzoplast Ltd. (Applicant, Adv. Amey Deshpande) v. Indorama Synthetic India Ltd. (Respondent, Adv. Shyam Dewani i/b Dewani Associates); condonation of delay for Section 34 Arbitration and Conciliation Act 1996 application challenging Arbitral Award dated December 30, 2023 (received January 24, 2024); dispute over filing date (May 3, 2024 vs May 13, 2024) and late condonation application of June 14, 2024 (144 days vs 120-day outer limit); Court held petition within time, power to condone existed; delay condoned subject to costs Rs.2,50,000/- payable within two weeks; petition listed for Case Management Hearing February 27, 2025; order dated January 31, 2025.
What did the court decide?
Interim Application finally disposed of with condonation of delay granted subject to payment of Rs.2,50,000/- costs to the Respondent within two weeks of upload of the order; on such payment the delay stands condoned and Commercial Arbitration Petition (L) No.16340 of 2024 to be listed under 'Case Management Hearing' caption on February 27, 2025.