Consent-based order permitting production of additional documents in pending commercial suits. Keywords: leave to produce documents; production of additional documents; Exhibit H; Exhibit I; admission and denial of documents; Bombay High Court Commercial Division; SAS Infra Projects (India) Pvt. Ltd. v. New Consolidated Construction Co. Ltd.; Interim Application No.1825 of 2025; Interim Application No.1896 of 2025; Commercial Suit No.122 of 2016; Commercial Suit No.117 of 2016; Abhay Ahuja, J.; decided 13 October 2025.
What did the court decide?
Leave granted to the Applicant/Plaintiff to produce the documents listed at Exhibit H (Interim Application No.1825 of 2025) and Exhibit I (Interim Application No.1896 of 2025); documents to be filed and served under Affidavit as per rules within four weeks; Defendant to file Statement of admission and denial within two weeks thereafter; documents to be marked in both Suits on 1st December 2025.