Devendra Khemraj Jain v. Harishchandra Basudev Sharma and Ors.
Case brief
What is this about?
Electricity meter disconnection; writ of certiorari sought against Respondent No.2 (supplier not named in judgment); restoration of electricity supply; ad-interim protection granted by coordinate Bench on 10.11.2023 and continued; bills Rs.240/- (residence, paid) and Rs.1450/- (shop, tendered but refused); landlord intervenor; electricity dues recoverable per law for any period; petitioner-landlord dispute left to appropriate proceedings; purpose of petition fructified; all contentions kept open; due process required for any future disconnection; disposed of, no costs. Bombay High Court, W.P. No. 12477 of 2023 with Interim Application 1005 of 2025, decided 07 April 2025.
What did the court decide?
No further relief; petition disposed of as its purpose had already fructified, with all contentions kept open; interim application disposed of; no costs.