Echjay Industries Private Limited v. Indus Powertech Inc.
Case brief
What is this about?
Consent disposal of a Section 9 Arbitration and Conciliation Act petition before the Commercial Division, Bombay High Court (Bharati Dangre, J., 05-12-2025) in Echjay Industries Private Limited v. Indus Powertech Inc (CARBP No.937 of 2025, with Contempt Petition No.33 of 2025 in CARBP (L) No.16800 of 2023). Supplier of forgings worth USD 10 million under a Master Supply Agreement claimed USD 9,938,891.88 overdue on invoices; buyer agreed to pay USD 5.5 million within seven working days pro-tem, without prejudice and subject to the final award, with arbitration to be invoked at the earliest; contempt petition listed for 08-01-2026. Keywords: Section 9 interim relief, pro-tem payment, consent order, Master Supply Agreement, invoices, forgings, commercial division.
What did the court decide?
By consent: Respondent (Indus Powertech Inc) to pay USD 5.5 million to the Petitioner within seven (7) working days as a pro-tem arrangement, without prejudice to the rights and contentions of both parties and subject to the final outcome of the Award; Petitioner to invoke arbitration at the earliest; Section 9 petition disposed of accordingly; Contempt Petition No.33 of 2025 listed on 8th January, 2026 for further consideration.