Abdul Rahim Khalilur Rehman v. Abdul Karim Khalilur Rehman
Case brief
What is this about?
Bombay HC, Bharati Dangre, J., 28-11-2025; CARBP No.469 of 2020 with CARBP No.811 of 2024; Section 9 and Section 17, Arbitration and Conciliation Act 1996; partnership firm M/s.Khalil Moulvi & Sons; Partnership Deed 06/06/2002 dissolved 2017; Trademark 'Moulvi' wordmark/device mark/logo with tagline 'Since 1921'; consent order 27/08/2021 restraining parties from 21/08/2019; injunction sought against Respondent No.1 and Respondent Nos.3 and 4; alter ego / corporate veil / lifting corporate veil; non-signatories bound by arbitration; Cox & Kings Limited vs. SAP India Pvt. Ltd. & Anr. (2025) 1 SCC 611 relied on; showroom opening Muscat Oman 14/11/2025; Section 9 petitions converted to Section 17 applications; additional pleadings on acting under/through; petitions disposed of.
What did the court decide?
Both Section 9 Petitions disposed of with liberty to the Petitioner to approach the learned Arbitrator by moving an appropriate application; the petitions permitted to be converted into Section 17 Applications for seeking necessary reliefs; the learned Arbitrator, if required, to permit additional pleadings on the point of acting under/through.