Mr. Sushil Kumar v. Bajel Projects Ltd.
Case brief
What is this about?
Sushil Kumar Rout v. Bajel Projects Ltd., Comm. Arbitration Application No. 193 of 2024, Bombay High Court, Somasekhar Sundaresan J., 14 January 2025 — Section 11 Arbitration and Conciliation Act 1996; existence of arbitration agreement; Clause 23 arbitration clause; Minutes of Meeting dated 13.08.2019 and 05.11.2020 held to be modification/amendment and continuance of Agreement dated 23.04.2018; 220 KV Sheopur substation civil work; scope of Section 11 confined to existence of formally executed arbitration agreement, validity and substance left to arbitral tribunal under Section 16; relies on Ajay Madhusudan Patel & Ors. Vs. Jotrindra S. Patel, 2024 SCC OnLine SC 2597; Prateek Pansare appointed Sole Arbitrator; no opinion on merits; application finally disposed of.
What did the court decide?
Appointment of Mr. Prateek Pansare, Advocate, as Sole Arbitrator to adjudicate the disputes and differences between the parties arising out of and in connection with the Agreement dated April 23, 2018; with directions that a copy of the order be communicated to the arbitrator within one week, statutory Statement of Disclosure under Sections 11(8) and 12(1) be forwarded within two weeks, parties appear before the arbitrator for conduct directions, and arbitral costs and fees be borne equally in the first instance subject to the final award on costs.