Mbpl-Kec Jv v. Maharashtra Rail Infrastructure Development Corportion Ltd.
Case brief
What is this about?
MBPL KEC JV versus Maharashtra Rail Infrastructure Development Corporation Ltd.; Bombay High Court, Ordinary Original Civil Jurisdiction; Commercial Arbitration Application No. 151 of 2024 with Commercial Arbitration Application No. 143 of 2024; Section 11, Arbitration and Conciliation Act 1996; appointment of Sole Arbitrator; Justice (Retd.) Gautam Patel; arbitration Clause 4.29.2; Contract Agreements dated January 16, 2020 and November 26, 2019; prior Section 9 petition disposed of by consensus vide Order dated July 22, 2022; disclosure under Sections 11(8) and 12(1); arbitral costs shared equally; decided February 27, 2025 by Somasekhar Sundaresan, J.
What did the court decide?
Appointment of Justice (Retd.) Gautam Patel, a former Judge of the Bombay High Court, as Sole Arbitrator to adjudicate the disputes between the parties arising out of and in connection with the Agreements; with ancillary directions: copy of the Order to be communicated to the Sole Arbitrator within one week; statutory Statement of Disclosure under Section 11(8) read with Section 12(1) to be filed in the Registry and furnished to the Respondents; parties to appear before the Sole Arbitrator with functional contact particulars, email communication constituting valid service; arbitral costs and fees of the Tribunal to be borne equally in the first instance, subject to any final Award on costs; all issues on merits kept open.