Union of India through Chief Project Manager/ Chief Engineer (N), Central Railway, Nagpur v. M/S Abhi Engineering Corporation Pvt. Ltd. Nagpur Thr. Its Authorized, Sanjay R. Vijaywargi
Case brief
What is this about?
Bombay High Court Nagpur Bench; Civil Application CAO 718/2025 in Misc. Civil Application 15013/2025 in Misc. Civil Appeal (ARBN) 407/2024(D); Chief Project Manager/CE(N) Central Railway, Mumbai vs M/s. Abhi Engineering Corpn. Ltd; arbitration appeal; issue of notice to non-applicant returnable 21.07.2025; time granted to file reply; liberty to file adjournment application before Arbitrator; arbitration hearing fixed 20.07.2025; Abhay J. Mantri, J.; advocates S.A. Chaudhari and S.O. Tapdiya.
What did the court decide?
Notice issued to the non-applicant returnable on 21.07.2025; time till 21.07.2025 granted to file reply; liberty granted to the applicant to file an adjournment application before the Arbitrator, which the Arbitrator may consider positively. ¶16