Executive Engineer, Bembla Project Division, Yavatmal v. Smt. Venubai Wd/O Nilkanthrao Didpaye and Others
Case brief
What is this about?
CAF No. 2488 of 2025 in First Appeal No. 524 of 2016, High Court of Judicature at Bombay, Nagpur Bench, decided 17-07-2025 by Abhay J. Mantri, J. Withdrawal of deposited compensation amount with accrued interest by applicants/respondent Nos. 2(a) to 2(c) and 3 to 7 after their Special Leave Petition was allowed and the Reference Court award was confirmed; no objection by appellant's counsel; payment through Power of Attorney dated 06-06-2025 to Applicant No. 2(a) Sarala Ashok Didpaye; Registrar (J) to transfer funds within four weeks; distribution as per award with affidavit within two weeks. Parties: Executive Engineer, Bembla Project Division, Yavatmal (appellant) v. Venubai wd/o Nilkanthrao Didpaye and others. Counsel: Ms. M.V. Babhulkar with Mr. M.A. Kadu for the appellant; Mr. Mohit Dube for respondent Nos. 2(a), 2(b), 2(c) to 7; Mrs. H.S. Dhande, A.G.P. for the respondents/State.