Bombay High Court, Aurangabad Bench [2025:BHC-AUG:16184]; Civil Application Nos. 11455 and 11456 of 2024 in FAST/27525/2024; Executive Engineer, Minor Irrigation Division, Osmanabad v. Abdul Razzak Chand Patel (Patil) and Ors; coram Shailesh P. Brahme, J.; decided 25.06.2025; delay condonation of 3040 days for first appeal against Reference Court compensation award; public exchequer; deposit of Rs.24,95,858/-; conditional release of 50% on undertaking and 25% on solvent surety; balance in Nationalized Bank; first appeal admitted; ad-interim stay confirmed; advocates: Dande Shrirang Shashishekhar (applicant), Madake Datta A. (respondent No.1), B. A. Shinde AGP (State).
What did the court decide?
Civil application for condonation of delay of 3040 days allowed in terms of prayer clause “A” subject to conditions permitting the respondent/claimant to withdraw 50% of the deposited amount with accrued interest on undertaking and 25% on solvent surety/security to the satisfaction of the Registrar (Judicial), balance invested in any Nationalized Bank; first appeal admitted with notice waived; ad-interim stay confirmed and the civil application for stay disposed of.