Nagnechi Construction Pvt. Ltd. v. Hella Infra Market Ltd. and 4 Ors.
Case brief
What is this about?
Section 34 Arbitration and Conciliation Act 1996; limitation for challenging arbitral award; service and despatch of arbitral award; letter dated August 6, 2021; postal department acknowledgment receipt; affidavit of Respondent No. 5 (arbitral institution); recall of order dated April 15, 2025; Nagnechi Construction Pvt. Ltd.; Hella Infra Market Ltd.; Bombay High Court, Ordinary Original Civil Jurisdiction; Somasekhar Sundaresan, J.; ARBP 78 of 2024; adjourned to July 8, 2025.
What did the court decide?
No final relief; interlocutory directions only — Respondent No. 5 (the arbitral institution) to file an affidavit confirming whether the Arbitral Award was served on the Petitioner in August 2021, no later than July 7, 2025; copies of the order to be served on Respondent No. 5 by the parties' advocates and the Registry; matter stood over to July 8, 2025. Neither limitation nor recall of the April 15, 2025 order was finally decided.