Mitual Dhiraj Shah v. Zee Infra Projects Private Limited
Case brief
What is this about?
Section 9 Arbitration and Conciliation Act 1996; interim relief; redevelopment premises; delayed handing over of possession; occupation certificate September 9 2021; attachment before future potential judgement; suit for recovery of damages by developer; Court Receiver demand rejected; undertakings; succession related disputes; estate of Ms. Bharti Shah; Mitual Dhiraj Shah & Anr.; ZEE Infra Projects Private Limited & Anr.; Somasekhar Sundaresan J.; High Court of Judicature at Bombay OOCJ; Arbitration Petition No. 32 of 2025; possession directed by June 25 2025 12:00 noon; compliance reporting June 26 2025; petition finally disposed of.
What did the court decide?
Under the Section 9 petition, Respondent No. 1-Developer is directed to hand over possession of the redeveloped premises attributable to premises owned by Ms. Bharti Shah to the Petitioners no later than June 25, 2025 at 12:00 noon, with requisite documents demonstrating title; undertakings recorded on both sides regarding estate/third-party claims; handover subject to outcome of the Developer's suit and without discharging any mutual dues; matter listed for reporting compliance on June 26, 2025.