Aditya Birla Finance Limited v. Jerath Path Labs
Bombay High Court (Somasekhar Sundaresan, J.) – Section 9, Arbitration and Conciliation Act, 1996
Case brief
What is this about?
Section 9 Arbitration and Conciliation Act 1996; ad-interim injunction; attachment of bank accounts; restraint on alienation of immovable property; loan default; dissipation of arbitration subject-matter; Jerath Path Labs; Aditya Birla Finance; Jalandhar properties; ex parte interim relief pending arbitration; Section 11 application liberty; Bombay High Court Arbitration Petition 290 of 2024.
What did the court decide?
Ex parte ad-interim reliefs as moulded: (i) temporary injunction restraining the Respondent, its agents and persons claiming under it from dealing with, selling, transferring, parting with possession of or creating third-party rights in three immovable properties at Jalandhar, Punjab (14, Link Road; H. No. 299/300, Eldeco Greens; #180, Street No. 4, Central Town); (ii) attachment of the Respondent's bank accounts with State Bank of India (A/c 00000031860265843) and Union Bank of India (A/c 539601010050524); reliefs to operate pending consideration of interim relief by the Arbitral Tribunal; liberty to file Section 11 application within 30 days; matter listed on April 30, 2025.