Ms Eff Tech Infra Engineers v. Ms Gammon Engineers and Contractors Pvt. Ltd.
Case brief
What is this about?
Eff Tech Infra Engineers versus Gammon Engineers & Contractors Private Limited; Bombay High Court, Original Side; Arbitration Application No. 292 of 2024; Justice Somasekhar Sundaresan; order dated February 4, 2025; praecipe; speaking to the minutes; clerical correction of order dated January 21, 2025; returnable date and stand over date corrected from February 3, 2025 to February 17, 2025; rest of order unaltered; no substantive adjudication, no statutes or precedents cited.
What did the court decide?
Correction of the order dated January 21, 2025: the returnable date and stand over date changed from February 3, 2025 to February 17, 2025; the original order to be corrected and made available to the parties; praecipe disposed of. ¶14