Ashok Shetty v. the Municipal Corporation of Gr.Mumbai
Case brief
What is this about?
The Court disposed of six writ petitions challenging a demolition order for a subdivided structure. It accepted a structural report, left open the question of liability for an external structure removed prior to the survey, and quashed the demolition order to allow the BMC time to assess compliance.
What did the court decide?
The order of demolition dated 10th March 2023 is quashed and set aside. Adverse BMC action is stayed for five weeks.