Vincent Paul Benedict Peris v. the Municipal Corporation of Greater Mumbai
Case brief
What is this about?
The court disposed of multiple writ petitions challenging a demolition order. The High Court quashed the demolition order and directed the BMC to act based on a supplementary survey report. The court allowed a stay on BMC adverse orders for five weeks to avoid summer vacation traumas and noted the standing permission's validity.
What did the court decide?
The demolition order of 10th March 2023 is quashed; the supplementary survey report is accepted; no adverse BMC order to be acted upon for five weeks.