Tulsidas Khimji Pvt. Ltd. and Anr. v. Union of India and Anr.
Case brief
What is this about?
Two writ petitions challenging impugned orders of the second respondent were listed for reply and interim directions. In WP 2652/2024 time was granted to file the reply; in WP 314/2024 a prima facie case was noted. Both petitions received ad-interim relief restraining enforcement of the impugned orders until 30 September 2024, with further listing dates fixed.
What did the court decide?
Ad-interim relief in terms of prayer clause (d) until 30 September 2024: no steps to implement/enforce the impugned orders dated 25.01.2024 (WP 2652/2024) and 15.11.2023 (WP 314/2024).
What the court decided
Digitally signed by MEERA MEERA MAHESH MAHESH JADHAV JADHAV Date: 2024.07.30 11:08:06 +0530
1/2 8-wp-2652 & 314-24.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 2652 OF 2024
Manish Jaswantlal Shah Partner Of M/s Shrilcon Shipping And Logistics Versus
Union Of India Thr The Secretary Ministry Of Law And Justice & Anr
...Petitioner
...Respondents
WITH
WRIT PETITION NO. 314 OF 2024
Tulsidas Khimji Pvt. Ltd. & Anr ...Petitioners Versus Union Of India & Anr ...Respondents
Dr. Sujay Kantawala a/w Mr. Ankit Dhindhale, Mr. Mahadeo Londhe and Mr. Avinash Limbola for Petitioner in both the petitions.
Parties & counsel
- petitioner
Manish Jaswantlal Shah
- respondent
Union Of India Thr The Secretary Ministry Of Law And Justice
- petitioner
Tulsidas Khimji Pvt. Ltd. & Anr
- respondent
Union Of India
Coram
Case details
As recorded by the court registry
All orders in this case
10 orders share this CNR
Similar cases
Judgements on the same questions, provisions and authorities, from every court