Harsha Infra Power Pvt. Ltd. v. Bharat Petroleum Corporation Ltd.
Case brief
What is this about?
Writ petition challenged an order debaring the petitioner from contracts with BPCL for three years. Since the petitioner had filed an appeal, the Court directed the Appellate Authority to conclude the appeal within three weeks without adjudicating the writ petition on merits.
What did the court decide?
Direction to the Appellate Authority to conclude the appeal within three weeks from the date the certified copy of the order is produced before it.