Vinod Infrastructure Pvt. Ltd. v. the Municipal Corporation of Greater Mumbai and 5 Ors.
Case brief
What is this about?
Coram addressed writ petitions filed by a housing society and its members against the Municipal Corporation regarding delayed fire safety clearance due to road encroachments. The court directed the Corporation to clear encroachments and issue notices for compound walls.
What did the court decide?
Corporation to initiate action to remove encroachments, issue notices for compound walls, and file progress affidavit by 2nd July 2024; matter posted for 4th July 2024. Justice Khata dissented regardi