What is this about?
The High Court allowed the second appeal and set aside the lower courts' decrees. It held that the notice for demolition was not barred by limitation as the appellant failed to prove the exact date of completion of the unauthorized construction. The burden lay on the appellant, and in the absence of evidence, the notice issued shortly after completion was valid.
What did the court decide?
Second Appeal allowed; judgment and decree of the Appellate Court reversed; notice held not barred by limitation; interim relief extended for 4 weeks.