Nariman Building Co-Operative Housing Society Ltd. v. Ramesh Madhukar Apte and 10 Ors.
Case brief
What is this about?
Co-operative society sought unhindered access to Flat 12A for court-ordered repairs and extension of time. Respondent No.10's counsel undertook to provide access from 6 May 2024 to 15 July 2024; repairs were covered by MCGM permission under section 342. Interim application disposed of.
What did the court decide?
Access undertaking recorded; interim application disposed of as nothing further remained to be adjudicated.