Mr. Owais Anwar Pechkar v. the Union of India, Thr the Secretary/Chief Engineer, Ministry of Road Transport and Highway and or
Case brief
What is this about?
Court disposed of a PIL regarding unfinished repair and widening of National Highway-66. Relying on departmental assurances, the court directed completion by December 31, 2024, and made the timeline binding with a contempt warning.
What did the court decide?
Directed that the entire stretch of National Highway-66 including road widening and repair works be completed by 31st December 2024.