Corporation’s demolition order dated 9 March 2021. A perusal of the order dated 5 July 2024 passed by the Division Bench of this Court reveals that the Corporation scheduled the demolition on 16 July 2024. However, on that day, the demolition process was hindered due to political influence, as a large mob gathered at the site. The informant filed the present FIR on 18 July 2024 as a last resort. Further, the orders passed in the Writ Petition reveal that the illegal construction was finally demolished in September 2024. From these events, it transpires that the informant took necessary steps at all material times but faced difficulties due to the casual approach of the Municipal Corporation. While the Corporation acknowledges not issuing construction permits to the applicant, it remained silent for years together and allowed the applicant to continue his wrongdoing until the Division Bench of this Court intervened in July 2024. This in itself suggests that the applicant, in connivance with the officials, has managed to stay out of trouble since 2020. That apart, the applicant claims to have acquired development rights from the co-owners of the land. However, the records do not indicate whether the land was partitioned or whether the applicant conducted any due diligence before commencing construction activities. Cognisant of the complexities involved, the applicant designed an intricate