Gajanan Anna Pawar and Others v. the State of Maharashtra and Others
Case brief
What is this about?
This judgment partly allowed multiple writ petitions and quashed impugned orders regarding compensation for farmers whose land was occupied by electricity towers and transmission lines. The court directed the Sub-Divisional Officer to determine if specific chart figures represent full compensation or require a 15% calculation under the Government Resolution.
What did the court decide?
Impugned orders dated 03/02/2020, 21/09/2020 and 14/02/2020 quashed and set aside. Respondent No.2 directed to decide the exact compensation amount and direct payment of deficit within 15 days.