the land belonging to the Petitioner for non-payment of royalty to the tune of Rs.17,23,78,243/-. The Petitioner submits that the Petitioner has undertaken the work of construction of two bridges, one at Mankoli and the other at Ranjaoli in Thane District. He submitted that the said work would be completed on or before 31st March 2017. He submitted that the impugned order is passed without giving any notice or without hearing the Petitioner. It is further submitted that the Petitioner has filed three Appeals under section 247 of the Maharashtra Land Revenue Code before the Collector, Thane and the fourth Appeal was decided by the Sub-Divisional Officer, Bhiwandi who was pleased to set aside the show cause notice and remand the matter back to the Tahasildar for the purpose of determination of royalty. The learned counsel for the Petitioner submits that this Court has by order dated 4th May 2016 was pleased to direct that the Appeals which are pending shall be decided within eight weeks. The learned counsel for the Petitioner submits that on priority basis, the order may be passed by the Sub-Divisional Officer for remanding the