M/S Shivam Constructions Prop Mr Shriram Prabhakar Munde v. the Water Conservation Department through Its Secretary Mumbai and Others
Case brief
What is this about?
Petitioners challenged rejection of their tender bid by respondent officials on eligibility grounds. The High Court held it could not go into disputed facts of fact. The Court directed the authority to reconsider the bid after hearing the petitioner and adjourned work order issuance for two weeks before considering the bona fides of the bid rejection.
What did the court decide?
The respondent no.4 is directed to consider the petitioner's case by giving hearing within one week and then pass an order on merits. The work order is not to be issued for a period of two weeks.