Alak Jyot Chs. v. Chief Executive Officer
Case brief
What is this about?
The High Court of Bombay disposed of a writ petition regarding the demolition of structures at a site, declaring the previous order complied with. No further action was taken.
The High Court of Bombay disposed of a writ petition regarding the demolition of structures at a site, declaring the previous order complied with. No further action was taken.
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
Dixit
IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION NO.2755 OF 2012
Alak Jyot CHS, Goregaon, Mumbai. .… Petitioner V/s. Chief Executive Officer, Slum Rehabilitation Authority, Bandra, Mumbai & Ors. …. Respondents
Mr. Yatin R. Shah for the Petitioner.
Mr. Kalpesh Patil, i/by Mr. Vijay D. Patil, for Respondent No.1.
Mr. Mohit P. Jadhav, A.G.P., for Respondent Nos.2 and 4.
Mr. Kamlesh R. Yadav for Respondent Nos.5, 7 to 9 and 11 to 20.
CORAM : S.C. DHARMADHIKARI &
DR. SHALINI PHANSALKAR-JOSHI, J.J.
DATE : 4 TH MAY, 2016.
P.C. :
on instructions, that after the earlier order was passed by this Court on 16th April 2016, the remaining structure at site has been demolished and the stilt area has been cleared. Since our order and direction dated 16th
April 2016 has been complied with, this Writ Petition need not be kept pending.
1/2
WP-2755-12.doc
3. The Writ Petition is disposed of in the above terms.
[DR. SHALINI PHANSALKAR-JOSHI, J.] [S.C. DHARMADHIKARI, J.]
2/2
WP-2755-12.doc
Alak Jyot CHS, Goregaon, Mumbai
Chief Executive Officer, Slum Rehabilitation Authority, Bandra, Mumbai
S.C. Dharmadhikari
Dr. Shalini Phansalkar-Joshi
As recorded by the court registry
Judgements on the same questions, provisions and authorities, from every court