Siddharth Nagar Parijat v. M/S. Sukushal Builders and Developers and 2 Ors.
Case brief
What is this about?
COURT OF JUDICATURE AT BOMBAY
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
901-S-847-14.DOC
Shephali
IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION SUIT NO. 847 OF 2014
Siddharth Natgar Parijat Co-op. Hsg. Soc. Ltd.…Plaintiff
Versus
M/s. Sukushal Builders & Developers & 2 Ors.…Defendants
Mr. Shreepad Murthy, i/b Anil Patel, for the Plaintiff.
Ms. Pratibha Patil, for the Defendants Nos. 1 and 2.
CORAM: G.S. PATEL, J DATED: 11th February 2015
PC:-
1.The plaint has been amended. The suit has been settled.
Consent Terms dated 9th February 2015 are tendered. These are
signed by the Advocates for the parties as also by the Honorary
Secretary of the Plaintiffs, an authorised signatory on behalf of the
1st and 2nd Defendants and by a parter of the newly added
Defendant, White Water Developers. The Consent Terms are taken
on record and marked ‘X’ for identification. Undertakings in the
Consent Terms are accepted as undertakings to the Court.
2.As against Defendant No. 3, the suit is allowed to be
withdrawn.
1 of 2
901-S-847-14.DOC
3. The suit is disposed of in accordance with the Consent Terms.
4. In view thereof, pending Notice of Motion does not survive and it is disposed of accordingly.
5. Refund of court fees in accordance with Rules.
6. All concerned to act on an authenticated copy of this order.
(G. S. PATEL, J.)
2 of 2
M/s. Sukushal Builders & Developers
White Water Developers
G. S. PATEL
As recorded by the court registry
Judgements on the same questions, provisions and authorities, from every court