Collector for granting approval to the works to be carried out by utilising the special grant of the State Government. The Superintending Engineer of the Public Works Department, the Chief Officer of the concerned Municipal Council and the District Project Officer are members of the Committee. Sub-clause (c) of clause 3 of the Government Resolution provides that works listed in the Schedule to the said Government Resolution should be carried out by the agency named in the schedule against the respective works. It also provides that for ensuring completion of the works on schedule, the Committee headed by the District Collector will have a power to change the agency mentioned in the schedule. Sub-clause (e) of clause 2 provides that if the Committee decides to get the work carried out through an agency other than the Municipal Council, No Objection Certificate (N.O.C.) of the Chief Officer of the Municipal Council will have to be obtained.