Dattatraya Bhanudas Shinde v. the State of Maharashtra and Another
Case brief
What is this about?
The High Court allowed a writ petition filed by a land claimant challenging the failure of the State of Maharashtra and the Collector, Ahmednagar, to pay land acquisition compensation and interest as per a Lok Nyayalaya compromise order. Respondents were directed to pay the amount along with interest and additional costs within three months.
What did the court decide?
Directed Respondents to pay compensation, interest, and costs of Rs.10,000 within three months.